質問38、 The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

 
 
 
 

質問39、 A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question

 
 
 
 

質問40、 The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.

 
 
 
 

質問41、 A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets.
What actions do you have to take to solve the problem?

 
 
 
 

質問42、 Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.

 
 
 
 
 

質問43、 Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

 
 
 
 

質問44、 Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

 
 
 
 
 

質問45、 Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?

 
 
 
 

質問46、 Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.

 
 
 
 

質問47、 You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

 
 
 
 

質問48、 Your customer’s projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?

 
 
 
 

質問49、 Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

 
 
 
 

質問50、 What could be a reason to use expert mode in the valuation method for results analysis?

 
 
 
 

質問51、 COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?

 
 
 
 

質問52、 What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.

 
 
 
 