82、Hotspot Question
Mark the layer where Dynamic Multicast Optimization should be activated.

83、A global cruise line company needs to refresh its current fleet. They win refresh the insides’ of the ship to be cost-effective and increase their sustain ability. They Mill replace the complete WLAN/LAN hardware of the ship. In this refresh, the company will not refresh Us current security requirements. The CIO also wants to limit the number of unused ports in the switches. Future expansion will always mean a refresh of hardware. They start with the smallest ship with a maximum of 800 guests. Each ship has a LAN infrastructure consisting of two core switches, up to 10 redundant distribution switches, and up to 500 access switches (400 cabins, 100 technical rooms). The Core switches are located in the MDF of the ship and the distribution switches are located in the IDFs of the ship. Each cabin and technical room gets one single access switch.
The cabling structure of the ship will not be refreshed. Each IDF is connected to the MDF by SMF. of which two pairs are available for the interconnect between the core and distribution. The length of SM fiber between MDF and IDF is less than 300 meters (930 ft) and the type used is OS1. Each cabin is connected by a single OM2 pair to the IDF, the maximum length is 60 meters (200 ft). Each technical room is connected by a single OM2 pail to the IDF, with lengths between
100 and 150 meters (320 and 500 ft).
For each cabin/technical room the customer is looking to replace their current fan-less 2530/2540 without changing the requirements, except they need to upgrade the uplink to distribution switch to 10GbE to handle the increased network traffic, and the technical rooms need redundant power.
The WLAN infrastructure will be 1:1 refreshed without new cabling or new AP locations. Their WLAN Infrastructure is based on the 200/300 series Indoor and outdoor APs running instantOS (less than 300 APs), the customer has no change in WLAN requirements.
The cruise line company will replace its current Internet connection before the LAN/WLAN refresh. The new Internet connection will provide a 99.8% uptime, which is needed to ensure the paid guest Wi-Fi is always operational. With this new internet connection, the CIO of the cruise line wants to base the design on the ESP architecture from Aruba because Internet connection is guaranteed. Based on the best practices and customer requirements, what is the correct WUN approach?

 
 
 
 

84、Drag and Drop Question
Match the deployment type with the usage scenario.

85、Which protocol does HPE’s Aruba ClearPass primarily use for network access control?

 
 
 
 

86、What are the considerations when using existing MMF and upgrading to equipment capable of 10 GbE speeds? (Select two)

 
 
 
 
 

87、ACME retail has 38 locations spread out across Ave US states and two provinces in Canada.
They are looking to grow 20% over the next two years. They have an HO with a staff of 200 employees. The organization has eight Regional Managers and two VPs who work from home and the road. Stores typically have 17 employees on average per location.
The two warehouses have a remote loading system and 20 employees each to load the trucks and fulfill the online orders. The warehouse has 40-foot ceilings and large metal racks to store inventory. The main location is 240K sq ft (22300 st) m) and the Canadian warehouse Is 130K sq ft (12100 sq ml. The forkllfts on the loading docks are equipped with a wireless tablet on board.
A typical store Is reportedly about 60,000 sq ft (5575 sqm) and smaller stores are planned at
25,000 sq ft ‘2320 sq mi. The locations need to expand the abilities to vendors that need to add setup displays or Interactive kiosks in the stores. The current Infrastructure was installed In 2015 and used wireless N technology in a coverage model. The wiring is CatS. and they are unsure of the fiber connections. The inventory is all placed on the floor when it is delivered to the local store. Inventory control is handled through Zebra barcode scanners, and they have had a lot of issues in getting signals throughout the stores and this makes monthly inventory difficult. The organization has a small help desk to troubleshoot issues that happen at the retail locations and PC support for the office. The company is looking to upgrade away from the current pbx system later this year. With the need to grow and cut costs, they are interested in moving the data to the cloud but need to get almost real-time inventory control for the online service to function.
The network has all been wired over the last ten years, but with the new systems being all wireless, they have seen the trend to offer wireless to all the vendors for their needs but also would like to allow employees, guests, and contractors all to use it. With the new IT director starting next week, the project has been set by the CTO of the company. The marketing group has asked how they can interact with the customers and get more info, while the IT support desk needs to cut staff in halt. The. office has an MDF and two IDFs located on floors one and two.
The HOF is in the basement, and you have multiple WAN circuits for the HO links. Each store has a local handoff from the cable company (ethernet) In the middle of the store in the office, so distance for the wiring is not an issue. The customer has budget concerns but does want something that could last 7+ years. Which two projects does the customer have in the planning state? (Select two)

 
 
 
 

88、Drag and Drop Question
Map the stakeholders to their roles.

89、Due to the type of transport used between regional data centers, the client is experiencing consistently delayed data transmissions. The response time between locations is consistently around 200ms.
What would this phenomenon be classified as?

 
 
 

90、You are responding to a customer’s Request for Proposal (RFP) for a new network infrastructure solution. The RFP outlines the customer’s desired features and technical outcomes but leaves several important design details unspecified.
At this stage in the proposal process, you are tasked with documenting the assumptions you’ve made in order to complete your design and address gaps in the RFP. These assumptions should reflect reasonable expectations that help guide the customer’s understanding of the solution and identify areas where further clarification may be needed.
What is a valid example of assumptions that should be presented to the customer in your RFP response?

 
 
 
 

91、XYZ Regional Hospital is an integrated healthcare system of hospitals, neighborhood health centers, and small doctor offices. XYZ Regional Hospital has recently merged with 4x neighborhood health centers and 125 doctor branch offices. The wireless, wired access, and AAA solutions are outdated and need to be replaced.
XYZ Regional Hospital is looking to future-proof and improve efficiency across all sites by enhancing wired and wireless access and migrating to a centralized and unified wired/wireless and policy management that can provide uninterrupted availability of all systems.
Locations:
– XYZ Regional Hospital is located in New York City
– Dila Health Center is located in City A
– Mount Health Center is located in City B
– Rock Health Center is located in City C
– Branch clinics are located at different locations across the United States Requirements:
– Provide, via management software, one single pane of glass to manage wired and wireless LANs, and VPNs across campus, branch, and remote via web/cloud architecture providing near real-time insight, troubleshooting tools, and Service Level performance reporting.
– Seamless integration across wired, wireless, WAN, SD-Branch, IoT
– Provide secure wireless access to all the employees of the Regional Hospital and partners, as well as provide wireless Internet access to medical citizens when they visit our facilities.
– All-access points must support the following features and specifications: 802.11.ax (Wi-Fi 6E Certified)
– Security options including WP2/WPA3, 802.1X with Radius secure authentication
– Identify and authenticate every wireless and wired device
– End-to-end role-based security
– Seamless mobility across the hospital for medical teams, patients, and visitors
– Cuts Wi-Fi deployment times from days to hours and enables Zero-Touch deployments across the site
– Establishes a resilient, future-ready network infrastructure with the intelligence, scalability, and intuitive toolsets to meet emerging needs
– Fully redundant branch solution with dynamic path selection to the hospital XYZ Regional Hospital is concerned about the performance of new latency sensitive applications that will be introduced when connected via wireless.
Which solution can address this concern?

 
 
 
 

92、Drag and Drop Question
What documents should be included in the solution proposal? (Place the correct items into the list at the right. Order is not important. Not all options will be used)

93、You hired a junior engineer to assist you with a large-scale network infrastructure project. The engineer has never worked on such a complex project before and wants to better understand the role that each stakeholder will play in the project. What is the role of Network Operations in this project?

 
 
 
 

94、A large multinational financial institution has contracted you to design a new full-stack wired and wireless network for their new 6-story regional office building. The bottom two floors of this facility will be retail space for a large banking branch. The upper floors will be carpeted office space for corporate users, each floor being approximately 100,000 sq ft (9290 sq m). Data centers are all offsite and will be out of scope for this project. The customer is underserved by its existing L2- based network infrastructure and would like to take advantage of modem best practices in the new design. The network should be fully resilient and fault-tolerant, with dynamic segmentation at the edge.
The retail space will include public guest Wi-Fi access. Retail associates will have corporate tablets for customer service, and there will be a mix of wired and wireless devices throughout the retail floors. The corporate users will primarily use wireless for connectivity, but several wired clients, printers, and hard VoIP phones will be in use.
The customer is also planning on renovating the corporate office space in order to take advantage of ‘smart office’ technology. These improvements will drive blue-dot wayfinding, presence analytics, and other location-based services.
The client decides that they would like for all of their exposed printer, conference room, and VoIP phone connections to be controlled by a stateful firewall.
What could be planned to ensure that these ports will meet the customer’s requirements?

 
 
 
 

95、What is the best practice for using VSX at the core of a 3-tier design?

 
 
 
 

96、XYZ Regional Hospital is an integrated healthcare system of Hospitals, neighborhood health centers, and small doctor offices. XYZ Regional Hospital has recently merged with 4x neighborhood health centers and 125 doctor branch offices. The wireless, wired access, and AAA solutions are outdated and need to be replaced.
XYZ Regional Hospital is looking to future-proof and improve efficiency across all sites by enhancing wired and wireless access and migrating to a centralized and unified wired/wireless and policy management that can provide uninterrupted availability of all systems.
Locations:
– XYZ Regional Hospital Is located In New York City
– Dila Health Center Is located in City A
– Mount Health Center is located In City B
– Rock Health Center is located in City C
– Branch clinics are located at different locations across the United States Requirements:
– Provide, via management software, one single pane of glass to manage wired and wireless LANs, and VPNs across campus, branch, and remote via web/cloud architecture providing near real-time insight, troubleshooting tools, and service Level performance reporting.
– Seamless integration across wired, wireless. WAN, SD-Branch, loT
– Provide secure wireless access to all the employees of the Regional Hospital and partners, as well as provide wireless Internet access to medical citizens when they visit our facilities.
– All-access points must support the following features and specifications: 802.11.ax (Wi-Fi 6E Certified)
– Security options Including WP2/WPA3, 80Z.1X with Radius secure authentication
– Identify and authenticate every wireless and wired device
– End-to-end role-based security
– Seamless mobility across the hospital tor medical teams, patients, and visitors
– Cuts Wi-Fi deployment times from days to hours and enables Zero-Touch deployments across the site
– Establishes a resilient, future-ready network infrastructure with the intelligence, scalability, and intuitive toolsets to meet emerging needs
– Fully redundant branch solution with dynamic path selection to the hospital XYZ Regional Hospital is looking tor an NAC solution to address its security challenges.
Requirements:
– fully redundant NAC solution for management and authentication
– wireless and wired authentication for the main hospital will be handled locally
– wireless and wired authentication for the health centers will be handled locally
– wireless and wired authentication tor the clinics will be authenticated against the main hospital NAC
– staff ustrs/devices should able to visit any site and haw the same experience
– support 35k devices
Locations:
– XYZ Regional Hospital is located in City 1 – 15k devices
– Dila Health center is located in City 2 – 8k devices
– Mount Health Center is located in City 3 – 5k devices
– Rock Health Center is located in City 4 – 4k devices
-125 branch clinics are located at different locations across the US – 2k devices Which solution meets the customer’s requirements?

 
 
 
 

97、it has been identified that the client’s existing network is having to retransmit packets due to possible hardware or configuration issues. A review of hardware configuration and transport reliability will need to be assessed prior to completing the new design.
What should this phenomenon be classified as?

 
 
 

98、ACME retail has 38 locations spread out across five US states and two provinces in Canada.
They are looking to grow 20% over the next two years. They have an HQ with a staff of 200 employees. The organization has eight Regional Managers and two VPs who work from home and the road. Stores typically have 17 employees on average per location.
The two warehouses have a remote loading system and 20 employees each to load the trucks and fulfill the online orders. The warehouse has 40-foot ceilings and large metal racks to store inventory. The main location is 240K sq ft (22300 sq m) and the Canadian warehouse is 130K sq ft (12100 sq m). The forklifts on the loading docks are equipped with a wireless tablet on board.
A typical store is reportedly about 60,000 sq ft (5575 sq m) and smaller stores are planned at
25,000 sq ft (2320 sq m). The locations need to expand the abilities to vendors that need to add setup displays or interactive kiosks in the stores. The current infrastructure was installed in 2015 and used wireless N technology in a coverage model. The wiring is Cat5, and they are unsure of the fiber connections. The inventory is all placed on the floor when it is delivered to the local store.
Inventory control is handled through Zebra barcode scanners, and they have had a lot of issues in getting signals throughout the stores and this makes monthly inventory difficult. The organization has a small help desk to troubleshoot issues that happen at the retail locations and PC support for the office. The company is looking to upgrade away from the current PBX system later this year. With the need to grow and cut costs, they are interested in moving the data to the cloud but need to get almost real-time inventory control for the online service to function.
The network has all been wired over the last ten years, but with the new systems being all wireless, they have seen the trend to offer wireless to all the vendors for their needs but also would be to allow employees, guests, and contractors all to use it. With the new IT director starting next week, the project has been set by the CTO of the company. The marketing group has asked how they can interact with the customers and get more info, while the IT support desk needs to cut staff in half.
The office has an MDF and two IDFs located on floors one and two. The MDF is in the basement, and you have multiple WAN circuits for the HQ links. Each store has a local handoff from the cable company (ethernet) in the middle of the store in the office, so distance for the wiring is not an issue.
The customer has budget concerns but does want something that could last 7+ years.
ACME Retail is using 4-post racks. Which rack mounting kit is better suited for this project?

 
 
 
 

99、XYZ Regional Hospital is an integrated healthcare system of hospitals, neighborhood health centers, and small doctor offices. XYZ Regional Hospital has recently merged with 4x neighborhood health centers and 125 doctor branch offices. The wireless, wired access, and AAA solutions are outdated and need to be replaced.
XYZ Regional Hospital is looking to future-proof and improve efficiency across all sites by enhancing wired and wireless access and migrating to a centralized and unified wired/wireless and policy management that can provide uninterrupted availability of all systems.
Locations:
– XYZ Regional Hospital is located in New York City
– Dila Health Center is located in City A- Mount Health Center is located in City B
– Rock Health Center is located in City C
– Branch clinics are located at different locations across the United States Requirements:
– Provide, via management software, one single pane of glass to manage wired and wireless LANs, and VPNs across campus, branch, and remote via web/cloud architecture providing near real-time insight, troubleshooting tools, and Service Level performance reporting.
– Seamless integration across wired, wireless, WAN, SD-Branch, IoT
– Provide secure wireless access to all the employees of the Regional Hospital and partners, as well as provide wireless Internet access to medical citizens when they visit our facilities.
– All-access points must support the following features and specifications: 802.11 ax (Wi-Fi 6E Certified)
– Security options including WP2/WPA3, 802.1X with Radius secure authentication
– Identify and authenticate every wireless and wired device
– End-to-end role-based security
– Seamless mobility across the hospital for medical teams, patients, and visitors
– Cuts Wi-Fi deployment times from days to hours and enables Zero-Touch deployments across the site
– Establishes a resilient, future-ready network infrastructure with the intelligence, scalability, and intuitive toolsets to meet emerging needs
– Fully redundant branch solution with dynamic path selection to the hospital XYZ Regional Hospital is planning a wireless site survey at its main campus. This must address recurring Wi-Fi coverage issues.
Which pieces of information will be required? (Choose two.)

 
 
 
 
 

100、A global furniture retail company called ‘No-Stair Inc.’ requests you design their new WLAN infrastructure for a global footprint. Each location of No-Stair Inc.’ has a similar layout: three small manager offices, a warehouse, and a ‘retail’ area. The ‘retail’ area and the warehouse together amount to 95% of the location. The IT department of the company Is minimally engaged In their LAN refresh so the CTO of the company has shared the information below Current WLAN Infrastructure Is based on the 802.11n “WlFI4Less” access-points series (both model 2013-INT (2.4 only Internal antenna) and model 2019-EXT (dual-band external antenna only)). These AP models are standalone without any centralized management. Last year ‘No- Stair InC ran a project called secure. It’ ensuring that all needed network security was Implemented to be fully compliant with their security standards. During this project, they also upgraded the AAA infrastructure to handle the Increased AAA requests. No additional Wi-Fi or security requirements are listed for this WLAN refresh, which means that ‘No-Stair Inc.’ will continue to use bridged SSIDs. with local breakout into different VLANs.
The CTO of No-Stair Inc.’ understands the need for you to ask additional questions to deliver the design. The questions may be sent in written form and will be answered within two weeks. Which additional question is correct in order to collect needed information for the WLAN design?

 
 
 
 

101、‘Don’t Buy at Us’ is a US-based retail company that is expanding Into Europe. They are expanding into EMEA with a regional headquarters called HQ2 inside The Netherlands. Their US- based headquarters HQ1 was refreshed last year based on the Aruba ESP architecture. You have treated the design for HQ? based on the same design as HQ1. a two-tier architecture.
The high level is shown below.

Switch BOM for this project based on Two Tier:
Collapsed Core: 2 x Aruba 8360-16Y2C in VSX (ISL 2x100GbE DAC)
Access Stack: 10 x Stack of 6200F 48G Class4 PoE 4SFP+ 740W (each stack has 4 members, VSF with 10GbE VSF links) (2 x 10GbE uplink per stack) During the presentation of your design to the CTO of “Don’t Buy at Us” you were informed about the changes they want you to incorporate into the updated design.
1. HQ2 will include the EMEA regional distribution center (EMEA-OISTR)
next to the HQ2.
2. Only two pairs of OS1 are available between HQ2 and EMEA-DlSTR.
3. The uplinks from all access stacks need to increase to 2 x 25GbE, the fiber in HQ2 and EMEA-DI5TRI is certified for 25GbE.
4. EMEA-DlSTR needs at least 7 x stack of Aruba 48 ports switches (each stack has 4 members).
Which answer based on best practice is presenting the correct Switch BOM tor the updated design?

 
 
 
 

102、Manufacturing ABC is an international, mid-sized company specializing in producing industrial equipment. They have been in the market for over two decades and have established themselves as a reputable player in their industry. However, due to rapid technological advancements, their current network infrastructure is outdated and struggling to keep up with the demands of modern manufacturing processes.
Manufacturing ABC’s network is a mix of multi-vendor legacy wired and wireless components, causing frequent downtime and hampering their production efficiency. The aging equipment leads to slow data transfer rates, unreliable connectivity, and increased vulnerability to cyber threats.
Fiber Cabling should be also upgraded as mostly OM2 is being used.
Compounding the network issues, the recent departure of the CTO has left the company without a clear direction for the network refresh project. There is a lack of consensus among the management team regarding the scope, budget, and timeline for the upgrade.
The primary objectives of the manufacturing customer are as follows:
– Improve network performance and reliability to enhance production processes and minimize downtime
– Enhance network security to protect sensitive data and intellectual property
– Streamline communication and collaboration among different departments within the organization
– Ensure scalability to accommodate future growth and technology advancements Manufacturing ABC seeks a comprehensive network refresh that includes the following components:
– Upgrading the wired infrastructure to high-speed Ethernet switches to support increased data transfer rates and reduce latency
– Implementing a robust wireless solution with enterprise-grade access points to provide seamless connectivity across the manufacturing facility
– Centralized network management tools to simplify administration and monitoring of the network Expectations:
The customer expects the network refresh project to be handled efficiently, with minimal disruption to their ongoing operations. They are looking for a reliable and experienced network solutions provider who can understand their unique manufacturing requirements and deliver a customized solution that aligns with their budget constraints. The manufacturing customer is keen on receiving clear project proposals and support in decision-making, given the recent change of the CTO.
Your role as a network solutions provider is to address their concerns, offer expert guidance, and present a well-defined plan to meet their objectives effectively.
You assume that the current network infrastructure does not have any wireless shadow IT equipment operated on the various floors/production sites, but you want to verify this. How could you find out if wireless shadow IT equipment is currently operational?

 
 
 
 

合格率 取得する秘訣はHPE7-A11認定試験エンジンPDF:https://www.goshiken.com/HP/HPE7-A11-mondaishu.html

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt